Construction Update Week of December 17, 2018

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours at the amenity deck and pools is in progress.
b. Window installation continues.
c. Wall layout, framing, and interior finishes are ongoing.
d. Elevator bracket and rails installation ongoing.
e. North and South Hoist take down 12/19/18 and 12/26/18.
f. NE 10th St. full Road closure:

• Duration: 01/02/19 -01/31/19
• Time: from 7:30 AM to 6:30 PM

2. 7th Street Apartments Project:

a. Retail Window installation continues.
b. Interior Punchout began.
c. Material deliveries on weekends.
d. Façade panels install continues.

3. Block D East:

a. Masonry installation continues throughout the building.
b. Elevators Installation is ongoing.
c. Stucco work continues.
d. Doors and door frames installations continue.
e. Installation Façade Metal panels and sub framing.
f. Installation of the steel supporting members for the louvers.
g. Installation of the temporary walls.

4. Site Work:

a. Full Road closure on NE 8th St between NE 1st Ave and NE 2nd Ave – South Side – Sidewalk Reconstruction.

• Duration 12/10/18 – 12/22/18

NOTE: All Concrete pours anticipated to start at 1am.