Construction Update Week of December 10, 2017

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; currently pouring levels 31 and up.
b. Window installation continues to follow concrete; currently installing level 22.
c. Wall layout, framing, and interior finishes are ongoing.
d. Buck Hoists, and North Crane will be Jumped.

2. 7th Street Apartments Project:

a. Concrete pour continues in tower– Levels 38 and up.
b. Concrete pours – garage deck levels 7.
c. Window installation continues – level 21.
d. Interior framing continues.

3. Block D East:

a. Forming and placing Concrete on Level 7M and 8 of amenities deck.
b. Forming and placing Concrete on Level 8 amenities deck.
c. Beginning slab on grade.
d. Continue MEP installation throughout the building.

4. Site Work:

a. Drainage installation along NE 10th St. from NE 1st Ave to NE 2nd Ave.

• Partial lane closure on NE 10th St.
• Closure Duration: December 11th thru December 22nd from 7:00 AM to 4:00 PM.

NOTE: All Concrete pours anticipated to start at 1am.