Construction Update Week of August 5, 2019

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Partial Lane Closure on NE 8th St. corner with 1st Ave.

• Duration: 08/01/19 – 08/31/19

• Time: from 7:30 AM to 6:30 PM

b. Partial Lane closure; most eastern lane on 1st Ave. between NE 8th and NE 10th Street

• Duration: 08/01/19 – 08/31/19

• Time: 7:30 AM to 6:00 PM

c. Interior finishes continue

d. Amenity deck continues

2. Block D East:

a. Sidewalk Partial closure – NE 2 Ave between NE 8 Street and NE 9 Street

• Time: 8PM – 5AM

• Duration: 08/12/19 – 08/26/19

b. Sidewalk Partial Closure – NE 2nd Ave Between NE 8 Street and NE 9 Street

• Time: 8AM – 4PM

• Duration: 08/07/19 – 08/12/19

c. Continue punch list throughout.

3. Site Work:

a. N Miami Ave from NE 8th ST to RR Tracks – Sidewalk Closure.

• Time: 8AM to 4PM

• Duration: 08/05/19 – 08/30/19

b. NE 10th ST from NE 2nd Ave to NE 1st Ave – Two Oak Plantings in Landscape Beds

• Street Closure on 08.07.19 (2 East Bound Lanes)

c. NE 2nd Ave and NE 7th ST (East Half) – Street Closure East / West Bound Lane – Day work

• Time: 8AM – 4PM

• Duration: 08/07/19 – 08/09/19

d. Sidewalk Closure – NE 2 Ave and NE 10 Street (East Half)

• Time: 8AM – 4PM

• Duration 08/12/19 – 08/13/19

e. Street Closure – NE 10th ST from NE 2nd Ave to NE 1st Ave (BVIEW)

• Two Oak Plantings in Landscape Beds

• Duration: 08/07/19 8AM – 4PM

4. MWC Luma

a. Chipping piles

b. Forming, Rebar and pouring tower foundations

c. Mat Pour – no street closure required

• Duration: Start 08/24/19 at Mid-night 12:00 AM – 08/24/19 05:00PM

NOTE: All concrete pour activities will start at Mid-night.

 

924803 924804 924802 924805



Contact Us