Construction Update Week of August 28, 2018

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; currently pouring level 59.
b. Window installation continues to follow concrete.
c. Wall layout, framing, and interior finishes are ongoing.
d. Elevator bracket and rails installation ongoing.
e. Elevator frames from 2nd thru 47th floors continue.

2. 7th Street Apartments Project:

a. Window installation continues on level 43.
b. Interior framing and MEP rough-ins continue in apartment units and corridors.
c. CMU installation in Garage continues.
d. Material deliveries on weekends.
e. Façade panels install continues.

3. Block D East:

a. Continue MEP installation throughout the building.
b. Miscellaneous metal installation.
c. Masonry installation continues throughout the building.
d. Barrier cable installation.
e. Elevators Installation.
f. Neutral Piers installation ongoing on north elevation.
g. Full street closure NE 8th St. between NE 1st Ave. and NE 2nd Ave.

• Duration: 09/10/18 to 09/12/18
• Time of Closure: 24 Hours

4. Site Work:

a. Road reconstruction NE 10th St. between 1st and 2nd Ave.

• Partial Street Closure Dates: 08/27/18 – 09/14/18.

b. Site Security Duct bank – Full Road Closure of NE 1st Ave and NE 7th ST

• Duration – 08/28/18 – 09/07/18
• Time of Closure: 8PM to 5AM

c. Installation of Drill Shaft for Mast Arm Signalization

• One day Partial Closure 08/28/18 – NE 2nd Ave and NE 9th ST
• Partial Closure of 1st Ave and NE 8th St. from 08/29/18 to 08/30/18

d. NE 8th St between N Miami Ave and NE 1st Ave – North Side – Sidewalk Reconstruction

• 08/27/18 – 08/31/18

e. NE 1st Ave between RR Tracks and NE 8th ST – Sidewalk Reconstruction – West Side

• 08/27/18 – 09/07/18

NOTE: All Concrete pours anticipated to start at 1am.