Construction Update Week of August 13, 2018

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; currently pouring levels 58 and up.
b. Window installation continues to follow concrete.
c. Wall layout, framing, and interior finishes are ongoing.
d. Elevator bracket and rails installation ongoing.
e. Elevator frames from 2nd thru 47th floors continue.

2. 7th Street Apartments Project:

a. Pool Deck amenities building concrete placement continues.
b. Window installation continues on level 43.
c. Interior framing and MEP rough-ins continue in apartment units and corridors.
d. CMU installation in Garage continues.
e. Material deliveries on weekends.
f. Façade panels install continues.

3. Block D East:

a. Continue MEP installation throughout the building.
b. Miscellaneous metal installation.
c. Formwork, rebar, pour concrete at Level 2 Mechanical opening.
d. Masonry installation continues throughout the building.
e. Barrier cable installation.
f. Elevators Installation.
g. NE 2nd Ave. full road closure between 8th and 9th St. (See attached drawing).

• Duration: 08/12/18 – 08/13/18
• Time of Closure: from 4PM on Sunday to 4 AM on Monday.

4. Site Work:

a. Road reconstruction NE 10th St. between 1st and 2nd Ave.

• Full Street Closure Dates: 07/12/18 – 08/17/18.

b. Road demolition NE 7th St. between NE 2nd and NE 1st Ave.

• Currently vacated street.

NOTE: All Concrete pours anticipated to start at 1am.