Construction Update Week of August 13, 2017

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; pouring floors 18 and 19.
b. Windows are being installed on floors 9-12.
c. Drywall and metal studs installation floor 9.
d. MOT – Water and Sewer connections; this work will be performed at night time only (8:00pm to 5:00am). NE 1st Ave. between 9th and 8th St.
Start Date: 08/28/17 End Date: 12/28/17

2. 7th Street Apartments Project:

a. Slab pour on levels 23 and 24.
b. Garage level 3 pour 1.
c. Garage level 2 pour 2.
d. Window install on levels 11-13.

3. Retail at Miami Worldcenter (Block D East):

a. Concrete pour on level 6.
b. Forming level 7.
c. Begin forming level 2 for west side

NOTE: All Concrete pours anticipated to start at 1am.