Construction Update Week of April 9, 2018

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; currently pouring levels 47 and
b. Window installation continues to follow concrete.
c. Wall layout, framing, and interior finishes are ongoing.
d. Full closure of NE 10th St. between NE 1st and 2nd Ave. for a Sewer connection – Continues.

• Closure Dates: 03/19/18 to 04/16/18.
• Closure time: 8 PM to 5AM.

e. Full closure of NE 1st Ave. between NE 8th and 9th St.

• Closure Dates: 03/11/18 to 04/15/18.
• Time of Closure: Night time closure only.

2. 7th Street Apartments Project: On Wednesdays the pours are taking place from 8PM to 11PM.

a. Concrete pour on the parapet wall on roof and Parking Garage continues.
b. Pool Deck – interstitial deck planter walls and framing of pool continues.
c. Window installation continues on levels 38 through 42.
d. Interior framing and MEP rough-ins continue in apartment units.
e. CMU installation in Garage.
f. Location: Partial lane closure on N. Miami Ave. between NW 6th St. and 8th St. by FPL.

• Duration: 03/29/18 thru 06/29/18
• Time of closure: 9PM to 8AM.

3. Block D East:

a. Forming roof top pools continues.
b. Slab on grade continues.
c. Continue MEP installation throughout the building and underground.
d. Handrail installation.
e. Crash wall ongoing.

4. Site Work:

a. Drainage installation along NE 1st Ave. between 8th and 6th street (East/West side).

• Parking lane and side walk closure on NE 1st Ave.
• Closure Duration: 02/26/18 – 04/10/18 8PM – 5AM.

b. Drainage installation along NE 8th St. between 1st and 2nd Ave. (South side).

• Full Street Closure dates: 04/11/18 – 04/25/18
• Time of Closure: 8:30Am – 4:30PM.

NOTE: All Concrete pours anticipated to start at 1am.

 