Construction Update Week of April 17th, 2017

For your information, the following is a list of “key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours on Slab, columns and walls continuing on level 7 – all concrete pours start at 1 am.
b. Masonry layout on 2nd thru 6th floor.
c. MEP rough in on the 3rd floor.
d. Sewer lines & man holes installation on the west side.

2. 7th Street Apartment Project:

a. Buck Hoist Installation: Drop Test.
b. 3rd Floor Masonry.
c. MEP installation is ongoing.
d. Level 6 – Elevator Concrete Pour; all concrete pours start at 1 am.
e. Level 11 to 12 shear wall pour.
f. Level 10 – East Tower concrete pour.
g. Pouring garage foundations continues.

3. Retail at Miami Worldcenter:

a. Concrete Pour – Grid Line D; all concrete pours start at 1 am.
b. Site Demolition continues.
c. Excavation on all footings and Site preparation for civil works continues.
d. Mobilizing contractors for equipment/material delivery.
e. Foundation steel installation continues.