For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount: a. Concrete pours on Slab, columns and walls continuing on level 7 – all concrete pours start at 1 am. b. Masonry layout on 2nd thru 6th floor. c. MEP rough in on the 3rd floor. d. Sewer lines & man holes installation on the west side.

2. 7th Street Apartment Project: a. Buck Hoist Installation: Drop Test. b. 3rd Floor Masonry. c. MEP installation is ongoing. d. Level 6 – Elevator Concrete Pour; all concrete pours start at 1 am. e. Level 11 to 12 shear wall pour. f. Level 10 – East Tower concrete pour. g. Pouring garage foundations continues.

3. Retail at Miami Worldcenter: a. Concrete Pour – Grid Line D; all concrete pours start at 1 am. b. Site Demolition continues. c. Excavation on all footings and Site preparation for civil works continues. d. Mobilizing contractors for equipment/material delivery. e. Foundation steel installation continues.