For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Partial Lane Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:

    • Duration: 04/16/19 – 04/26/19
    • Time: from 7:30 AM to 6:30 PM

b. Partial Lane closure; two most eastern lanes on 1st Ave. between NE 8th and NE 10th Street.

    • Duration: 04/15/19 – 04/19/19
    • Time: 24 Hours

c. Building Enclosure at Podium continues
d. Interior finishes continue
e. Amenity deck continues

2. Block D East:

a. Elevators testing is ongoing and nearing completion.
b. Installation of the metal fins started on the north elevation.
c. Installation of the steel supporting members for the louvers continues.
d. Off-site utilities installation along 2nd Avenue continues.

3. Site Work:

a. Full Closure of NE 8th St. Between NE 1st and NE 2nd Ave due to Gas line installation.

    • Time: 7AM to 4PM
    • Duration 04/22/2019 to 04/24/2019

b. Partial Lane Closure (2 Traffic Lanes) on NE 2nd Ave between NE 8th ST and NE 9th ST

    • Demolition / Water and Sewer / Electrical Mains/ Irrigation Mains
    • Time: 8AM to 4PM
    • Duration 04/15/2019 to 05/03/2019

4. MWC Luma

a. Demolition of Unforeseen Concrete Foundations
b. Grading Site to 9.00NGVD
c. Haul Off of Site Soil and Demolition Soils

NOTE: All Concrete pours anticipated to start at 1am.